More windows, window boards and plaster board

This week work has continued to fit such remaining windows as have arrived. We have the perfect set of circumstances: most of the windows are in place and have their double glazing units, but there are some frames in place with as yet missing glass, and some glass units in the garage with as yet missing frames. We are led to believe that this will be rectified in the next couple of weeks, and in the meantime some of the missing glass has been temporarily replaced by boarding so that the plastering may proceed. When we visited yesterday Pat was fitting some window sills upstairs as further preparation for plastering. Downstairs we shall have mainly oak sills.

Today Sion's uncle and his fellow plasterer are hard at work boarding out the first floor, which has the higher proportion of stud walls. Their work fitting board to the solid walls and then skimming everywhere will follow. They could be on site for 6 weeks, as their work inside will be followed by rendering the majority of the outer walls (the remainder will be boarded with larch).

It was quite a new take to see that all of the upstairs spaces are now defined, where before we could see through the studwork. The first impression, of course, is that the spaces are smaller, but as you move from room to room there are naturally more distinct spaces than before - even the sizes of cupboards are clear now.

We also spent a few minutes replacing marker posts in the field - they had been cropped with the maize - in the hope that we can arrange with Hayden and Pat to have the area fenced while the field is free of stock.

one of the pair of windows in the bay in bedroom 3 (to be Elizabeth's study) .....

..... and on the inside


one of the two windows at the front of bedroom 4 is in place

window (with protective tape still in place) between porch and hall

boarding in place in the downstairs shower room to allow the towel rail to be fixed

the window above where the kitchen sin will be .....

..... and from the outside

the north-west corner of bedroom 4

looking through the family bathroom to bedroom 3

shower plumbing in place in bedroom 1's ensuite, with the view through the cupboard and landing still open

insulation at the apex of the landing ceiling

this drain connection is getting more complicated - it will take waste and bath and basin water from the family bathroom and bedroom 2's ensuite

neat work to install the shower waste of bedroom 1's ensuite .....

..... and bedroom 2's ensuite shower waste

we like the copper work above the utility room

this is how a sliding window goes in

one of the side windows in bedroom 1

bedroom 2's window and view

the utility room's window is in

this is the small side window in the sitting room

one of the pair of bifold doors in the sitting room going in

this is how the house is looking from the community garden

a bifold leaning in front of the fixed window in the sitting room

the frames of the picture windows in bedroom 1 are in place, but their glass units haven't arrived yet ....



..... so now they are boarded up to allow plastering to proceed

here we are marking out part of the land we are gaining from the adjoining field

just a small part of the plasterboard stock needed to board a whole house

boarding in progress in the upstairs cupboard and bedroom 1's ensuite

in bedroom 2 the ensuite and small wardrobe are now distinct

bedroom 3 (Elizabeth's study) is now boarded

looking back from the front bedroom along the landing - no views through the studwork now

window board in place in bedroom 4



Comments

Popular posts from this blog

Eighteen months have passed

Gravel, gates, and a working wood-burning stove

We have boundary walls