More blocks and the beginning of the first floor
We have had a week or so of much improved weather, so it was a pleasure to make our traditional late Friday afternoon visit to the plot in sunshine and under blue skies. A couple of days of block moving and laying this week have got the first floor underway. The laying of the first course is an awkward job, involving the cutting of lots of blocks to fit between the joists. We are encouraged by continuing signs of good practice: the joists are being supported by acrow props to ensure that they don't move while the fitted blocks set (and under the weight of the blocks being stored on them) and lengths of visqueen are temporarily in place to minimise the dropping of mortar into the cavities - avoiding a sure cause of future damp problems.
It's perhaps worth clarifying that all the concrete blocks are structural but will eventually be covered. The inside walls will be plastered, and outside we plan a combination of render and timber cladding.
Next stop, scaffolding.